Project Type

BMS 

Location

1-3 Brixton Rd, Vassal, London SW9 6DE, United Kingdom

Property Type

Commercial

Background

A section of the largest site by Workspace is to undergo a BMS upgrade. The main works are on the control of the boilers and pumps as well as the monitoring of the plant room, heating and electrical metering. The controllers will be linked to the new Optergy Enterprise servers for remote control and monitoring of the site.

The Solution

We were the most cost-effective solution offering the latest technology. We installed IP based controllers which was a massive speed upgrade over their old legacy controllers.
We installed an Optergy server and connected this remotely so their facility managers could access the site remotely. We developed all new graphics that made the system clear to use and interpret.

For the 1 AHU that had controls issues, we discovered during the cutover that the zone temperature sensor was faulty, and this was causing overheating and massive gas usage.